CASE STUDY: SHYMKENT  W.W.T.P.

Case StudyShymkent W.W.T.P.
Location
Kazakhstan
Target
Sludge Elimination
Population Equivalent
1000 000
Flowrate
150 000 m3/day
Treated wastewater
Municipal
Project Initiation
07/01/2024
ParameterUnitsInput (average)Sludge Production Before Application (Average) - tn/day, (dry solids)Sludge Production After Application (average) - tn /day (dry solids)Reduction
Suspended Solidsmg/l28037.5 - 401.5 - 295%
CODmg/l500
TNmg/l50
TPmg/l10

REMARKS

  • The odour problem has been solved and H2S reduced
  • The electricity consumption in the aerobic zone is reduced by at least 30% post-application of Ydro bacterial products
  • The SVI values in the sedimentation tanks have been improved
  • With Ydro Process® sludge for disposal is reduced by 90%

CASE STUDY: MARIJAMPOLE W.W.T.P.

Case StudyMarijampole W.W.T.P.
Location
Lithuania
Target
Sludge Elimination, Odour Control
Population Equivalent
100 000
Flowrate
12 500 m3/day
Treated wastewater
Municipal
Project Initiation
08/2022
ParameterUnitsInput during application (Average)Output during application (Average)
CODmg/l97670
BOD7mg/l4609.0
TNmg/l6812.3
TPmg/l140.36
SSmg/l3863.5
NO3-Nmg/l12
NH4-Nmg/l450.05
Sludge Production Before Application (Average) - tn/day (80% water content)16-20
Sludge Production After Application (Average) - tn /day (80% water content)2-3
Reduction80-90%

REMARKS

  • Elimination of excess sludge (digested sludge – primary and secondary)
  • Elimination of odours
  • Reduction of the operational cost

CASE STUDY: SOUTHERN GREECE W.W.T.P.

Case StudySouthern Greece W.W.T.P.
LocationSouthern Greece
TargetSludge Elimination
Populations Equivalent200 000
Flowrate38 000-40 000 m3/day
Treated wastewaterMunicipal
ParameterSuspended SolidsCODTNTP
Unitsmg/lmg/lmg/lmg/l
Input (average)100400707
Sludge Production Before Application (average)30-35 (tn/day)
Sludge Production After Application (average) 0 (tn /day)
Reduction100%

REMARKS

  • The total reduction of excess sludge occurred with anaerobic digestion stage not in operation
  • The electricity consumption reduced to approximately 15% after the application of our bacterial products
  • The SVI values in the sedimentation tanks were improved

CASE STUDY: NORTHERN GREECE W.W.T.P.

Case StudyNorthern Greece W.W.T.P.
LocationNorthern Greece
TargetSludge Elimination
Populations Equivalent120 000
Flowrate29 000 m3/day
Treated wastewaterMunicipal
ParameterSuspended SolidsCODTNTP
Unitsmg/lmg/lmg/lmg/l
Input (average)2504005512
Sludges Production Before Application (average)
20-25 (tn/day)
Sludge Production After Application (average)0(tn/day)
Reduction100%

REMARKS

  • Total reduction of excess sludge
  • The electricity consumption in the aerobic zone has reduced to approximately 25% after the application of the Ydro Process®
  • The SVI values in the sedimentation tanks were improved

CASE STUDY: VERIA W.W.T.P.

Case StudyVERIA W.W.T.P
Location
Northern Greece
Target
Sludge Elimination
Population Equivalent
60 000
Flowrate
11 000 – 13 000 m3/day
Treated wastewater
Municipal
Project Initiation
15/07/2012
ParameterSuspended SolidsCODTNTP
Unitsmg/lmg/lmg/lmg/l
Input (average)4005007515
Sludge Production Before Application (average)15-20 (tn/day)
Sludge Production After Application (average) 0 (tn/day)
Reduction100%

REMARKS

  • The plant also receives up to 100 tn/day of external sludge from other wastewater treatment plants, which is equivalent to a population of 500 000 people
  • The electricity consumption in the aerobic zone has been reduced to at least 50% after the application of our bacterial products

CASE STUDY: ANDRATX  W.W.T.P.

Case Study
Andratx W.W.T.P.
Location
Mallorca, Spain
Target
Sludge & Energy Reduction
Population Equivalent
20 000
Flowrate2500 m3/day
Treated wastewater
Municipal
ParameterSuspended SolidsCODTNTP
Unitsmg/lmg/lmg/lmg/l
Input (average)n/a649
649
Sludge Production Before Application (average)
6 (tn/day)
Sludge Production After Application (average)
2 (tn/day)
Reduction65%

REMARKS

  • Reduction of excess sludge
  • The electricity consumption in the aerobic zone has reduced to approximately 40% after the application of the Ydro Process®
  • Cost reduction

CASE STUDY: DRUSKININKAI W.W.T.P

Case StudyDruskininkai W.W.T.P.
LocationSouthern Lithuania
TargetSludge & Odour Elimination
Populations Equivalent15 000
Flowrate4 600 m3/day
Treated wastewaterMunicipal
ParameterSuspended SolidsCODTNTP
Unitsmg/lmg/lmg/lmg/l
Input (average)n/a449
549
Sludge Production Before Application (average)
6 (tn/day)
Sludge Production After Application (average)
0.5 (tn/day)
Reduction90%

REMARKS

  • Total reduction of excess sludge
  • Improved effluent parameters
  • The odour problem was solved
  • Cost reduction